Wednesday, January 25, 2012


The final phase of the Irrigation Renovation is in full swing and we’re currently installing the main-line pipe that will supply water to the Grand Pines and the Clubhouse. This process is occurring around the Pines putting green, practice range and other areas in the nearby vicinity. Due to the fact cart paths will be impacted for a short period we’ll need to redirect golf cart traffic at times. Directional signs will be posted so please use caution during your travels in the immediate area.



Thursday, December 15, 2011

WATER MATTERS  #13
by Brad Wilkins
Irrigation Task Force

This article will discuss the completion of Phase II of the Irrigation Project and will present the schedule for Phase III and the job completion.  The schedule presented below, is dependent on the delivery of pipe and materials.  Much of the Phase III Rainbird material is on hand allowing  us to avoid their announced price increase.

By the time that this article goes to press, all the testing and punch list work for Phase II will have been completed.  The crews for the most part went home for Christmas and left a small work force in place for anything that might come up.  They will be returning through the period of January 2nd and January 14th, 2012.

Site preparation and pipe deliveries is scheduled for this period.  On or about January 12th, they will be working around the Country Club tying into the large diameter pipe that was installed during Phase II.  They will be installing a 16" diameter line from the end of the large line installed in Phase II and it will terminate near the #1 tee of the Grand Pines.  From there, 10" lines will be installed.  In addition, some of the irrigation system around the clubhouse will be started.

Work will then be moved to Timber Point Blvd.  This is scheduled for early in February and is expected to take about a month.  With the main line installed on Timber Point Blvd, the crew will tie into that line and do the Highlands Golf Course.  This portion of the work will be pressure tested, inspected and all punch list work completed.

The crew will then return to the clubhouse grounds and complete that work.  This work is scheduled to completed by the first week in May.  Work will then begin on the back nine of the Grand Pines starting with hole #18.  This portion of the golf course will be closed until July.  When the punch list work is complete, the back nine will be opened and the front nine of the golf course and the driving range  will be closed. The crew will start on hole #1.

Work will then go on until the golf course and driving range is completed and the pressure test and punch list work is complete. 

Keep in mind, that the schedule discussed above, is dependent on the delivery of material and weather conditions.  The schedule calls for all work to be complete by the middle of October.

Monday, October 17, 2011

Mainline pipe fusion near Abilene Gate.
Isolation valve installation during phase 2 rescom.
Mainline bore under Grand Club Drive.
Pipe pulling along Grand Club Drive.

Wednesday, September 14, 2011


WATER MATTERS #12
Brad  Wilkins IrrigationTask Force

Continuing our series of articles to keep you informed of the status of the irrigation system installation, this article will bring you up to date on Phase I and Phase II.

Phase I of the irrigation project is complete.  All testing, including the system pressure test, has been successfully completed. Sean Hyduk of Aqua Turf International, our irrigation service consultant, has completed all Phase I inspections and has signed off on all the punch list items. He has also programmed the central control computer and provided as built drawings to our Grounds Superintendent Eric Czarnecki.

Lynn Setelius, our comptroller has closed out the AFE (Authorization for Expenditure), with a $4,170 contract cost under run. In addition to the cost under run we sold some of the components of the old system and collected more than $5,000. There were fourteen (14) relatively minor change orders (plus and minus) included in the cost under run and none of the contingency funds were touched.  The project objectives of an average water distribution efficiency (DU) of 84% and reduced watering window (8 hours or less) were more than met as has been previously reported. Other project objectives included improved playability of the Lakes Golf Course and the appearance of both the golf course and common grounds along Timber Pines Blvd. That success is more subjective but is very evident.

The Internal Audit Committee has completed a review of the Phase I contract process and found no major discrepancies. The impact on residents was minimal and the Lakes golf course reopened on schedule. These successes are the result of a good design, a good contract, good administration by the consultant and Timber Pines staff and good performance by the contractor Mike Roach Incorporated.

Phase II work which began in May and has been moving forward nicely. The golf course portion of Phase II has been completed and the Hills Golf Course opened for play on August 18 as scheduled. The pressure test for Phase II golf has been conducted and was successful. The DU audit of the Hills Course will be conducted within the next 30 days. A punch list has been developed and the open items are being addressed.

The remainder of Phase II work involves the common grounds along Grand Club Drive (North and South). You have probably seen the work crews which started on Grand Club South at the intersection of Timber Pines Blvd. This work is scheduled to proceed through the winter.

Please look for the periodic updates posted by Eric in the Friday Flash, the monthly newsletter and the irrigation blog @ www.timberpines.com. He does an excellent job in keeping the community informed of the project status.

Looking forward, the Phase lll work is tentatively scheduled for early in May, 2012.  The work to be included is the Grand Pines, the Highlands, Timber Point Blvd and the area around the Club House, PAC and the Tennis Courts.