The final phase of the Irrigation Renovation is in full swing and we’re currently installing the main-line pipe that will supply water to the Grand Pines and the Clubhouse. This process is occurring around the Pines putting green, practice range and other areas in the nearby vicinity. Due to the fact cart paths will be impacted for a short period we’ll need to redirect golf cart traffic at times. Directional signs will be posted so please use caution during your travels in the immediate area.
Wednesday, January 25, 2012
The final phase of the Irrigation Renovation is in full swing and we’re currently installing the main-line pipe that will supply water to the Grand Pines and the Clubhouse. This process is occurring around the Pines putting green, practice range and other areas in the nearby vicinity. Due to the fact cart paths will be impacted for a short period we’ll need to redirect golf cart traffic at times. Directional signs will be posted so please use caution during your travels in the immediate area.
Thursday, December 15, 2011
WATER MATTERS #13
by Brad Wilkins
Irrigation Task Force
by Brad Wilkins
Irrigation Task Force
This
article will discuss the completion of Phase II of the Irrigation Project and
will present the schedule for Phase III and the job completion. The schedule presented below, is dependent on
the delivery of pipe and materials. Much
of the Phase III Rainbird material is on hand allowing us to avoid their announced price increase.
By
the time that this article goes to press, all the testing and punch list work for
Phase II will have been completed. The
crews for the most part went home for Christmas and left a small work force in
place for anything that might come up.
They will be returning through the period of January 2nd and January
14th, 2012.
Site
preparation and pipe deliveries is scheduled for this period. On or about January 12th, they will be
working around the Country Club tying into the large diameter pipe that was
installed during Phase II. They will be
installing a 16" diameter line from the end of the large line installed in
Phase II and it will terminate near the #1 tee of the Grand Pines. From there, 10" lines will be
installed. In addition, some of the
irrigation system around the clubhouse will be started.
Work
will then be moved to Timber Point Blvd.
This is scheduled for early in February and is expected to take about a
month. With the main line installed on
Timber Point Blvd, the crew will tie into that line and do the Highlands Golf
Course. This portion of the work will be
pressure tested, inspected and all punch list work completed.
The
crew will then return to the clubhouse grounds and complete that work. This work is scheduled to completed by the
first week in May. Work will then begin
on the back nine of the Grand Pines starting with hole #18. This portion of the golf course will be
closed until July. When the punch list
work is complete, the back nine will be opened and the front nine of the golf
course and the driving range will be
closed. The crew will start on hole #1.
Work
will then go on until the golf course and driving range is completed and the
pressure test and punch list work is complete.
Keep
in mind, that the schedule discussed above, is dependent on the delivery of
material and weather conditions. The
schedule calls for all work to be complete by the middle of October.
Monday, October 17, 2011
Wednesday, September 14, 2011
WATER
MATTERS #12
Brad Wilkins IrrigationTask Force
Brad Wilkins IrrigationTask Force
Continuing our series of
articles to keep you informed of the status of the irrigation system
installation, this article will bring you up to date on Phase I and Phase II.
Phase I of the irrigation
project is complete. All testing, including
the system pressure test, has been successfully completed. Sean Hyduk of Aqua
Turf International, our irrigation service consultant, has completed all Phase
I inspections and has signed off on all the punch list items. He has also
programmed the central control computer and provided as built drawings to our
Grounds Superintendent Eric Czarnecki.
Lynn Setelius, our
comptroller has closed out the AFE (Authorization for Expenditure), with a $4,170 contract cost under run. In
addition to the cost under run we sold some of the components of the old system
and collected more than $5,000. There were fourteen (14) relatively minor change
orders (plus and minus) included in the cost under run and none of the
contingency funds were touched. The project
objectives of an average water distribution efficiency (DU) of 84% and reduced
watering window (8 hours or less) were more than met as has been previously
reported. Other project objectives included improved playability of the Lakes
Golf Course and the appearance of both the golf course and common grounds along
Timber Pines Blvd. That success is more subjective but is very evident.
The Internal Audit
Committee has completed a review of the Phase I contract process and found no
major discrepancies. The impact on residents was minimal and the Lakes golf
course reopened on schedule. These successes are the result of a good design, a
good contract, good administration by the consultant and Timber Pines staff and
good performance by the contractor Mike Roach Incorporated.
Phase II work which began in
May and has been moving forward nicely. The golf course portion of Phase II has
been completed and the Hills Golf Course opened for play on August 18 as
scheduled. The pressure test for Phase II golf has been conducted and was
successful. The DU audit of the Hills Course will be conducted within the next
30 days. A punch list has been developed and the open items are being
addressed.
The remainder of Phase II
work involves the common grounds along Grand Club Drive (North and South). You
have probably seen the work crews which started on Grand Club South at the intersection
of Timber Pines Blvd. This work is scheduled to proceed through the winter.
Please look for the periodic
updates posted by Eric in the Friday Flash, the monthly newsletter and the
irrigation blog @ www.timberpines.com. He does an excellent job in keeping the
community informed of the project status.
Looking forward, the Phase
lll work is tentatively scheduled for early in May, 2012. The work to be included is the Grand Pines,
the Highlands, Timber Point Blvd and the area around the Club House, PAC and
the Tennis Courts.