Installation of Tee valves. Note the attention to detail in installation.
Temporary Remote unit installed on #2 Tee of Lakes course. This will give us the ability to test/control IC System immediately following the installation of irrigation components on individual holes.
All Underground utilities within Timber Pines were located prior to commencement of Irrigation Renovation Phase 1.
Karl Interrante, Mike Roach Project Manager, performs first irrigation head splice for RainBird IC System.