WATER MATTERS #13
by Brad
Wilkins
Irrigation
Task Force
This
article will discuss the completion of Phase II of the Irrigation Project and
will present the schedule for Phase III and the job completion. The schedule presented below, is dependent on
the delivery of pipe and materials. Much
of the Phase III Rainbird material is on hand allowing us to avoid their announced price increase.
By
the time that this article goes to press, all the testing and punch list work for
Phase II will have been completed. The
crews for the most part went home for Christmas and left a small work force in
place for anything that might come up.
They will be returning through the period of January 2nd and January
14th, 2012.
Site
preparation and pipe deliveries is scheduled for this period. On or about January 12th, they will be
working around the Country Club tying into the large diameter pipe that was
installed during Phase II. They will be
installing a 16" diameter line from the end of the large line installed in
Phase II and it will terminate near the #1 tee of the Grand Pines. From there, 10" lines will be
installed. In addition, some of the
irrigation system around the clubhouse will be started.
Work
will then be moved to Timber Point Blvd.
This is scheduled for early in February and is expected to take about a
month. With the main line installed on
Timber Point Blvd, the crew will tie into that line and do the Highlands Golf
Course. This portion of the work will be
pressure tested, inspected and all punch list work completed.
The
crew will then return to the clubhouse grounds and complete that work. This work is scheduled to completed by the
first week in May. Work will then begin
on the back nine of the Grand Pines starting with hole #18. This portion of the golf course will be
closed until July. When the punch list
work is complete, the back nine will be opened and the front nine of the golf
course and the driving range will be
closed. The crew will start on hole #1.
Work
will then go on until the golf course and driving range is completed and the
pressure test and punch list work is complete.
Keep
in mind, that the schedule discussed above, is dependent on the delivery of
material and weather conditions. The
schedule calls for all work to be complete by the middle of October.