WATER
MATTERS #12
Brad Wilkins IrrigationTask Force
Brad Wilkins IrrigationTask Force
Continuing our series of
articles to keep you informed of the status of the irrigation system
installation, this article will bring you up to date on Phase I and Phase II.
Phase I of the irrigation
project is complete. All testing, including
the system pressure test, has been successfully completed. Sean Hyduk of Aqua
Turf International, our irrigation service consultant, has completed all Phase
I inspections and has signed off on all the punch list items. He has also
programmed the central control computer and provided as built drawings to our
Grounds Superintendent Eric Czarnecki.
Lynn Setelius, our
comptroller has closed out the AFE (Authorization for Expenditure), with a $4,170 contract cost under run. In
addition to the cost under run we sold some of the components of the old system
and collected more than $5,000. There were fourteen (14) relatively minor change
orders (plus and minus) included in the cost under run and none of the
contingency funds were touched. The project
objectives of an average water distribution efficiency (DU) of 84% and reduced
watering window (8 hours or less) were more than met as has been previously
reported. Other project objectives included improved playability of the Lakes
Golf Course and the appearance of both the golf course and common grounds along
Timber Pines Blvd. That success is more subjective but is very evident.
The Internal Audit
Committee has completed a review of the Phase I contract process and found no
major discrepancies. The impact on residents was minimal and the Lakes golf
course reopened on schedule. These successes are the result of a good design, a
good contract, good administration by the consultant and Timber Pines staff and
good performance by the contractor Mike Roach Incorporated.
Phase II work which began in
May and has been moving forward nicely. The golf course portion of Phase II has
been completed and the Hills Golf Course opened for play on August 18 as
scheduled. The pressure test for Phase II golf has been conducted and was
successful. The DU audit of the Hills Course will be conducted within the next
30 days. A punch list has been developed and the open items are being
addressed.
The remainder of Phase II
work involves the common grounds along Grand Club Drive (North and South). You
have probably seen the work crews which started on Grand Club South at the intersection
of Timber Pines Blvd. This work is scheduled to proceed through the winter.
Please look for the periodic
updates posted by Eric in the Friday Flash, the monthly newsletter and the
irrigation blog @ www.timberpines.com. He does an excellent job in keeping the
community informed of the project status.
Looking forward, the Phase
lll work is tentatively scheduled for early in May, 2012. The work to be included is the Grand Pines,
the Highlands, Timber Point Blvd and the area around the Club House, PAC and
the Tennis Courts.